Hi SAP Community, I am working on a requirement in SAP PS (CJ20N) where the Basic Start Date ( PLFAZ ) and Basic Finish Date ( PLSEZ ) entered at the Project Definition header need to be automatically copied to the Level-1 CAPEX WBS element when saving the project. Business Logic: Special Projects ( RFTA , CHTA 😞 Only one Level-1 WBS exists, so it directly inherits the Project Definition dates. Standard Projects ( RFPA , RFCA , CHPA , etc.): Needs to identify if the Level-1 WBS is CAPEX (checking ‘C’ at character 10 / token 3 of the coding mask) before assigning the dates.